September 2008 - as advertised on ebay
October 2008 - bringing it home
November 2008 – the first strip down
November 2008 - the new chassis
November 2008 – more stripdown
November 2008 – the new firewall
November 2008 – throttle linkage
details
November 2008 – bringing
the new firewall home
November 2008 –
stripping the second vehicle down
December
2008 – finishing the second vehicle stripdown, carting the relics to the tip
December 2008 – stripping the
original vehicle down to a rolling chassis with engine/gearbox
January 2009 – more
stripping down, cleaning the engine/gearbox
March 2009 – abrasive
blasting and painting
March 2009 – removing the engine
and gearbox
April 2009 – stripping
down the last of the chassis
May 2009 – sorting out the rims
and tyres
May-July 2009 –
mechanical repairs
June-July 2009 – painting the chassis
June 2009 – fixing the firewall
July 2009 – painting the bits
hanging off the chassis
July 2009 – more chassis
painting
August 2009 – a rolling
chassis
August 2009 – cleaning up the
steering wheel
August 2009 – repairing the fuel tank
October 2009 – front door
hinges
October 2009 – brake lines installed
December 2009 – re-install
engine and gearbox
March 2010 – re-install the shrapnel
on the engine
April 2010 – starting up the engine
May 2010 – sorting out the
rear suspension
June 2010 – installing the firewall
July 2010 – installing the clutch and brakes
August 2010 – cleaning up the body
July 2010 – assembling the body
August 2010 – sorting out
the instruments
September 2010 – installing
the cappings and electrics
October 2010 – installing the soft top
October 2010 – installing the wipers
October 2010 – Roadworthy and registered
November – December 2010 – Rework jobs
July 2011 – power steering part
1
July 2011 - power steering
part 2